Emerald Hills Elementary Replacement

FEATURES

  • Designed to meet the needs of approximately 550 K-5 students
  • Allow for flexible learning spaces throughout the school
  • Meet the needs of Specialists including PE, Music, Technology and STEM
  • Modern infrastructure
  • Site plan that allows for future location of Early Learning Center on campus

BENEFITS

  • Replace oldest, unimproved school in the district
  • Campus design that allows for safe bus and car zones

SCHEDULE (approximate)

  • Planning/Design: September 2016- February, 2017
  • Bidding: April/May, 2017
  • Construction: June, 2017-August, 2018

STATISTICS

Location: 19515 S Tapps Dr E

Square footage: Approximately 55,000

Classrooms: 24 classrooms K-5 with Specialist classrooms for Learning Specialists, PE, Music, Technology and STEM

Student Capacity: Approximately 550 students

Budget projection: $28 million

Estimated Open Date: September, 2018

Architect: Erickson-McGovern Architects

Contractor: TBD 
 

 